- This expansion - which doubled the existing warehouse's 30,000 sf size - required a four (4) phased construction to ensure continuous, 24/7 operation of the warehouse
- Stormwater management of the site during and after construction was paramount to the City of Norfolk and the Client, and was achieved in part through use of a bio-retention basin
- Retrofitting of the original 30,000 sf warehouse was part of the overall enhancement and included restrooms, locker rooms, office, and equipment and truck maintenance areas
- Construction Cost: $3,000,000
Meet the Structural Engineer >
|